Construction of a new 69/12-kV Vine Substation at the southwestern corner of the intersection of Vine Street and Kettner Boulevard, just west of Interstate 5 (I-5). Project included relocation of approximately nine existing 12-kV distribution circuits utilizing a combination of existing and new underground distribution conduit, as well as loop-in an existing 69-kV power line (TL604) to the Vine Substation.

Client

San Diego Gas & Electric Company

Status

Completed

Location

San Diego County

Assignment

Document Control Services

Services

Pride Resource Partners (PRP) provided services in the area of document control that included support to the project team and contractor with management and audit of all documentation in the client’s Document Management System. PRP also trained the client’s and contractor’s employees on the proper document policies and procedures.